Data Centres

10 things we learned at Capacity Europe 2026

19 October 2026
8 minutes
From two-year generator queues to the UK's fibre consolidation fight, the 25th Capacity Europe showed an industry where the constraints on AI demand, not the demand itself, now set the agenda.
Wiring the AI Boom
Wiring the AI Boom

AI demand was taken as a given at Capacity Europe 2026. Across three days at the InterContinental London, The O2, from 13 to 15 October, the harder conversations were about what stands in the way of meeting it: power, grid timelines, equipment, skilled labour, long-haul routes, community consent and the discipline of the capital paying for it all.

Here are the ten takeaways that defined this year’s event:

Machines now out-request humans online

Colt chief strategy officer Avijit Singh opened with a milestone: in June, machine-generated web page requests overtook human ones for the first time, at 57.4% against 42.6%, according to Cloudflare data. He said machine traffic could exceed human traffic by 100 times within five years.

The practical consequence is a shift from north-south traffic, cloud to user, to east-west traffic between agents and data centres. That raises the bar on latency, resilience, automation and observability, and moves security towards verifying machine identity rather than users. “Now we have crossed the threshold,” Singh said.

That shift is reaching how services are bought. Speakers expect AI agents to compare and renegotiate contracts on customers’ behalf, so operators will need machine-ready sales channels. “It’s not search optimisation anymore; it’s machine optimisation,” as one put it.

Inference is pulling compute beyond FLAP-D

Speakers repeatedly pointed to inference, not training, as the next wave. Verizon’s Jeff Hulse cited McKinsey research suggesting 2026 is the first year inference investment matches training. Valerie Cussac of Orange Wholesale said AI workloads are already hitting networks, particularly between data centres.

That is reviving the edge, this time as a question of location. T Wholesale’s Dimitrios Rizoulis said the search for edge locations to host inference in Europe is “very, very high”. DE-CIX CEO Ivo Ivanov said each millisecond of latency equals roughly 80km, putting agentic and physical AI applications within 100km to 150km of the inference they depend on.

Meta, which has deployed edge sites since around 2013, called the industry’s earlier retreat from edge “a major missed opportunity” and said edge capacity is now scarce. Ivanov described Lisbon, Madrid and Barcelona as a “distributed digital capital”, a sign that Europe’s data centre map is spreading well beyond FLAP-D.

Connectivity can no longer be an afterthought

Digital Realty’s Paula Cogan said network planning still comes too late in many builds. “A data centre is simply a large fridge without a deep connectivity ecosystem,” she said. Colt’s Joe Scattareggia said new fibre builds take 12 to 18 months, and Equinix said it began planning connectivity for one North London campus with Colt five years before opening.

Exa Infrastructure CEO Jim Fagan described a “fundamental shift” in demand, and Salam’s Amjad Arab said AI workloads can require up to 36 times more fibre than traditional applications.

Demand is also spreading beyond the major hubs into local markets, enterprise sites and regional exchanges. “The whole network will be required,” said euNetworks CEO Marisa Trisolino. Panellists still warned against overbuilding, particularly in metro markets where demand remains uncertain.

Long-haul and subsea are the overlooked bottleneck

FLAG’s Paul Abfalter argued that compute investment is running well ahead of the networks connecting it, describing “really significant underinvestment” in data centre-to-data centre long-haul capacity and growing constraints on several international routes.

Sparkle CEO Enrico Bagnasco said geopolitics is preventing the industry from building enough subsea capacity to meet demand over the next five years, notably around the US and the Middle East. New routes are coming: Orange announced a joint venture with Equitix and MDM to deliver Pisces, a roughly 3,125km, 16-fibre-pair system linking Ireland, France, Spain and Portugal without transiting the UK. Exa also completed new Milan-Zurich and Paris-Vienna long-haul routes during the week.

Sovereignty now means owning physical infrastructure

Orange Wholesale CEO Michael Trabbia used his day two keynote to argue that the AI race has moved from models to infrastructure. With more than $800 billion being spent on data centres this year, heading past $1 trillion, connectivity has become a strategic asset.

“You cannot talk about sovereignty without talking about physical infrastructure,” he said, pointing to the risk that a foreign government could switch off a service for geopolitical reasons. Orange is backing that view with a 400MW data centre joint venture in France and plans for 2.5 million kilometres of fibre by 2028.

Securing supply now matters more than price

Telehouse’s Ozgur Duzgunoglu said generators can take two years to arrive and high-voltage transformers 12 to 18 months. Operators are committing to suppliers before designs are final. “We should be worried about capacity,” said Greenscale’s Miriam van Kooperen.

Start Campus has made “procure first, design around it” a company mantra, according to Nelson Pinto de Magalhaes, who now measures procurement savings in days rather than euros. Operators are also moving to performance-based rather than product-based specifications so they can switch suppliers when a preferred vendor cannot deliver.

Skilled labour is the next pinch point. Pinto de Magalhaes said lining up equipment, installers and commissioning teams in the same window is now harder than securing the equipment itself. Van Kooperen expects mechanical, electrical and plumbing trades to see the greatest shortages by 2029, particularly in new locations with power but little data centre construction experience.

Grid certainty matters more than incentives

Power remained the dominant constraint, but the bigger problem is not knowing when it will arrive. One investor said a grid operator can promise a connection in 36 months and deliver in 48, leaving the developer to carry a year of extra capital. “There’s no trouble in finding capital,” he said. “The real issue we have is just getting certainty on the timelines.”

National Grid strategic demand director David Atkins said the UK transmission owner is building three times as much network in this five-year period as in the last. He said flexibility of just 1% to 2% from data centres could unlock significant spare capacity, and called the next three to six months pivotal for connections reform.

Elsewhere the wait is longer. Telehouse’s Duzgunoglu said securing power in Frankfurt can take five to seven years, and Meta said anchoring a new facility takes around 18 months in the US against three to four years, sometimes more than five, in Europe. That is pushing operators towards behind-the-meter supply. “The grid’s not your only option,” said hydrogen power provider GeoPura.

The licence to operate is the industry’s open problem

Community consent came up on almost every stage. Digital Realty’s Cogan said she now sometimes hesitates before telling people what she does, and called for a European version of Infrastructure for America, the US consortium Digital Realty formed with competitors to explain what data centres do for communities.

Telehouse’s Mark Pestridge described “a massive gap between what we call digital dependence and digital understanding”. Greenscale CEO Daniel Thomas said operators should commission and publish independent “ripple effect” studies of their local economic impact.

Engagement can change minds. Nomad Futurist’s Simon Allen cited a CyrusOne project in Milan where a community survey went from more than 70% opposed to more than 70% in favour once the operator responded to residents’ concerns.

The UK fibre consolidation fight went public

nexfibre CEO Rajiv Datta used the Fibre Investment Stage to challenge the CMA’s provisional findings on its £2 billion Netomnia acquisition, calling the regulator’s view “completely divorced from financial reality”. He argued the UK cannot sustain three physical networks in every postcode. “Having more networks does not make stronger challengers,” he said.

Datta also questioned rival bidder CityFibre’s finances, a characterisation CityFibre rejected, pointing to continued growth and a £900 million equity commitment from shareholders. Both sides agree consolidation is coming; the dispute is over who leads it. The CMA’s final decision is due by 15 December.

Capital and value will follow the bottlenecks

ING managing director Jeroen Kleinjan said lenders want contracted cash flows, secured power and experienced sponsors. “Value will accrue around bottlenecks,” he said, naming power, strategic sites, scarce routes and trusted interconnection.

Investors said risk has moved to both ends of the deal. AI has made sites less location-sensitive, so a remote campus either lands a gigawatt customer or becomes a stranded field, while some AI tenants carry far shorter credit histories than hyperscalers. Eurofiber offered the disciplined alternative: COO Eric Kuisch said its €2.2 billion refinancing reflected investor confidence in an open-access B2B model that secures revenue before building.

Traffic alone will not pay. Mobile UK CEO Hamish MacLeod said UK mobile revenues have fallen about 30% while traffic has grown 40 times, and LINX CEO Jennifer Holmes cautioned that “value isn’t necessarily revenue”.