Delivering megawatts on a predictable date is the problem.
Europe’s digital infrastructure industry has no shortage of customers, and capital is available for projects that can prove they will deliver. Turning that into delivered capacity is the struggle, according to senior executives at the Digital Infra Leaders roundtable in London on 12 October.
Seven in ten attendees polled during the session, around 30 people, said they expect a grid connection to take more than 18 months. They rated the industry’s current handling of community acceptance at around four out of ten.
The session, held under the Chatham House Rule, brought together data centre operators, connectivity providers, hyperscale customers, banks, lawyers and network owners. It set out to answer two questions: what turns a location into bankable capacity, and can hub creation be made repeatable?
The answer that emerged was consistent. Power, permitting, grid access and community consent now decide where Europe’s next hubs are built, and certainty of delivery has become the deciding factor for customers and capital alike. As one participant put it: “If we were allowed to spend the trillion dollars, we would love to.”
Certainty is the currency
Asked what makes a location durable, 81% of attendees chose deliverable megawatts with clear amortisation milestones. Permitting and competitive power followed.
Customers and operators in the room agreed on what drives decisions: a predictable ready-for-service (RFS) date. End users now work backwards from that date, checking whether power, land and even on-site contractors are secured. If they are not, the customer moves to the next site.
“They just need certainty,” one operator said.
A lender in the room described the customer as the starting point rather than one factor among many. Before a project reaches an investment committee, it needs a stable, investment-grade offtaker and a contract structure that matches the asset. Without those, the conversation does not begin.
Even then, competition for capital is intense, because so many projects now have strong investment-grade counterparties. Banks are prioritising those on their balance sheets, and balance sheets alone are unlikely to be enough, with fixed income playing a growing role. Capital that is available increasingly comes with tighter restrictions on how it can be used.
The result is a bias towards established markets. Existing hubs offer “known knowns”, one participant said, while new markets carry far more unknowns for developers and their backers.
The map is moving east and south
84% of attendees said growth will expand beyond the traditional FLAP-D markets of Frankfurt, London, Amsterdam, Paris and Dublin, with power availability shaping the new geography.
Participants described two network topologies overlapping. The older one was built around people, connecting cities and regions. The newer one follows power, water, land and infrastructure, while still being pulled towards population as AI moves closer to users. Corridors that were never popular are gaining traction as a result.
One table summed up its view in three words: “east and south”. Locations raised across the room included Warsaw, Madrid and wider Spain, Norway, and second- and third-tier German cities. Turkey was raised as a wildcard, given its geographic position. Participants suggested governments in eastern and southern Europe may be more willing to prioritise the economic activity data centres bring, and communities there more welcoming.
Paris divided opinion. Some pointed to its nuclear-backed, low-carbon power. Others with experience of building there described it as a hard market, with resistance at municipal level.
The established hubs are not standing still. Cloud demand continues to drive availability zone expansion in markets such as Frankfurt and London. But metros are regionalising, with growth shifting up to 50km from the central business district. Amsterdam and Dublin were cited as constrained by permitting.
Participants also noted that training and inference may settle in different places, with latency-tolerant training able to go wherever the economics are best. Few were willing to pick a winner. “There’s no single market that is likely to win,” one operator said, warning that a change in regulation or grid policy can reshape a market within six months.
Speculative demand is clogging the queue
Attendees ranked power price, permitting, grid connection time and community acceptance as their biggest constraints, and said all four are likely to get worse.
In the UK, discussion centred on connection queues swollen by speculative applications from data centres and battery storage. Recent connections reform thinned out generation projects but left the demand side largely untouched, and current rules require network operators to treat every application equally.
Regulators are moving. In July, Ofgem opened a consultation on clearing speculative data centre projects from Britain’s demand connections queue, which it said had grown from 41GW to 125GW between November 2024 and June 2025. Around 73GW of data centre demand was referenced in the consultation, which proposed a commitment fee and new progress milestones and closed on 16 September (Capacity coverage).
Several remedies were discussed: pricing mechanisms to discourage speculative applications, US-style commitments to long-term network charges, and a formal definition of “strategic demand” so viable, funded projects can be moved up the queue. Participants said the UK still lacks a clear definition, although government consulted on prioritising strategic demand in March.
Participants also raised the idea of network operators publishing locations where capacity could be delivered fastest, so developers could build hubs around them, provided those sites have the fibre and latency customers need.
Supply chain was flagged as a hidden constraint. A queue full of projects that may never be built spreads equipment and engineering capacity thinly, slowing the projects that will.
Permitting is an even bigger challenge for international connectivity than for data centres. A data centre deals with one local authority, while a subsea or cross-border route may require consent from many, each with little stake in the overall project.
Some delegates said the only reliable workaround today is to go where connections are available sooner, or to look at behind-the-meter power.
Losing the narrative
Community acceptance is climbing the agenda. 74% of attendees called it a strategic risk, and 70% expect it to have a high influence on future investment decisions. Yet they scored the industry’s current effectiveness at roughly four out of ten.
The main sources of local opposition, in attendees’ view, are electricity consumption, water use, a lack of perceived local economic benefit and poor communication. Participants argued that several of these concerns rest on misconceptions, particularly around water use and local heat.
Part of the problem is history. A decade ago few people knew what a data centre was, and customers often demanded confidentiality. The sector is now in the public eye daily but still shares relatively little. One operator warned that if the industry does not explain itself, the vacuum “will be filled with negative sentiments”. Local mayors, participants said, are increasingly wary of approving projects for fear of backlash.
When polled on solutions, 77% backed more transparent community engagement and 71% wanted greater sharing of local economic benefits. The practical proposals from the room were consistent:
- Engage early, before planning applications are lodged, through public forums and local councillors.
- Build an industry playbook of shared principles, then tailor it to each community’s specific concerns.
- Hire locally. Teams with people who know the area and its decision-makers fare better.
- Budget for giving back, whether through scholarships, local facilities or support for sports clubs.
- Keep educating the public on how much of daily life depends on digital infrastructure.
“It’s all about early engagement,” one attendee said.
Connectivity providers said they often sit in the back seat of this debate. Connectivity accounts for less than 10% of a data centre project’s cost and plays little part in the power concerns driving opposition, yet their networks depend on these projects going ahead.
From the back seat to the front
Several tables concluded that the industry needs to be far more assertive with policymakers. Large telecoms groups lobby Brussels with dedicated teams, but the wider digital infrastructure sector has rarely spoken with one voice on what it needs, participants said.
Data centres are becoming a political issue in Europe as well as the US, and they are not vote winners. One attendee said UK government understanding of the sector has improved, but that the issue needs more voices across government.
One proposal was to bring grid connection, permitting and energy procurement into a single national digital policy framework, with a one-stop process for major projects. Participants noted that governments are now competing for this investment at the highest level.
The session ended on a paradox. Demand is not the issue, and capital is there for projects that can prove delivery. Deliverability itself is the constraint. Participants were encouraged to take one change back to their organisations, whether contributing to an industry playbook on community engagement or working more closely with their grid operator.
In a market where time to megawatts decides who wins, even marginal gains in predictability are worth having.
The Digital Infra Leaders roundtable took place in London on 12 October 2026, ahead of Capacity Europe. Comments were made under the Chatham House Rule.
Related stories:
- 833 opposition groups, one global pattern: Why data centre resistance looks so different by country
- 175km and rising: Europe’s data centre capacity is moving beyond its big five hubs
- Grid connection delays force shift to power-first data centre site selection
- UK energy regulator promises power crackdown for data centres
- Beyond FLAP-D: Why Europe’s next wave markets are moving centre stage
- Two-year generator waits push data centre builders to procure before they design

Capacity Europe 2026
The 25th anniversary edition of Capacity Europe 2025 will bring together 3,500+ decision-makers from the global connectivity and digital infrastructure community.