All operators are encouraged to meet the tests, but they are mandatory only for “strategic” data centres seeking government help to speed up their connection. The government has not yet said which sites will qualify. The covenant estimates the UK will need 6GW of AI data centre capacity by 2030, roughly three times its current operational capacity of around 2GW.
A new Ministerial Control Centre, chaired by the minister for AI, will decide which sites get support. That can include reserved or reallocated grid capacity and, for exceptionally strategic projects where other measures fall short, temporary on-site generation while they wait. Strategic sites must also agree a Local Benefit Plan committing substantial investment in their communities.
Alongside the covenant, the government published a draft National Policy Statement for Data Centres, out for consultation until 8 January 2027. It sets the framework for large projects, indicatively those with at least 100MW of IT load, seeking consent through the Nationally Significant Infrastructure Project regime.
Healey framed the measures around sovereignty, telling MPs that “nowhere is the necessary role for the state clearer than in AI”. The covenant sits alongside an AI and cybersecurity package worth more than £700 million, including £140 million more for the Sovereign AI Unit and £60 million for Sovereign AI’s R&D Procurement Scheme. The first-year capital allowance also rises from 40% to 50%.
An undefined label
Trade body techUK said the covenant recognises domestic data centre capacity as key to growth, sovereign compute and national resilience. It added that using new powers to speed up connections could clear long-standing barriers to investment.
But techUK noted that “strategic data centre” has yet to be defined. It also named energy as one of the Budget’s main weaknesses, warning that the UK remains uncompetitive on energy affordability and risks losing digital infrastructure investment.
The developer view
Peter Griffiths, founder and executive chairman of Argyll Data Development, called the covenant “potentially the more significant announcement”, ahead of the extra £60 million for the Sovereign AI Fund.
Funding British AI companies “achieves little if the infrastructure they depend on cannot get connected to the grid”, he said. Prioritising strategic, efficient sites with local benefits was “the right direction”, but “the test will be how quickly it turns proposed capacity into working infrastructure”.
Griffiths argued that Scotland’s renewable resources make it a natural place to connect generation, storage and AI compute, rather than “treating every new data centre as another demand on an already constrained grid”.
Analysis: the queue still has to move
The covenant’s strongest levers, reserving future capacity, reallocating connections freed up by others and transferring pre-2030 contracts, largely move strategic sites up the grid queue rather than shortening it.
Ofgem has said the connection queue grew 460% in the first half of 2025, with data centres accounting for at least 73GW of the pipeline. At a recent Capacity roundtable in London, 70% of infrastructure leaders said they expect connections to take more than 18 months.
The consequences are already visible given that earlier this month Microsoft walked away from Nscale’s planned Loughton site which was once billed as the UK’s largest sovereign AI data centre. That decision came after the site was told grid power may not arrive until the early-to-mid 2030s. In Scotland, councils must now notify ministers of any data centre application over 50MW, and such projects require an environmental impact assessment.
The on-site generation allowance could bridge some of those gaps, but the covenant’s value to developers will depend on two things the Budget left open: how many sites are classed as strategic, and how quickly reserved capacity reaches them.
The procurement test
Mark Boost, CEO of UK cloud provider Civo, said the government had “set out the right principles” on procurement and backing British SMEs, but that “the real test is yet to come”. UK public cloud spending, he said, “has defaulted to US hyperscalers for years”.
Civo, which is developing sovereign AI models with Locai Labs under Project Mercury, wants the government to “commit to buying from UK-owned and operated providers”. Boost warned the plans would go awry “if its procurement bravery fails to match its rhetorical ambition”.
Connectivity missing from the plan
Lee Myall, CEO of Neos Networks, welcomed the covenant’s focus on grid access but said the same joined-up thinking must extend to digital connectivity.
Neos research found that connectivity constraints have forced 38% of large UK businesses to keep AI workloads more centralised than planned, while 34% have moved workloads to another region entirely. Myall has previously told Capacity that connectivity, not compute, will decide whether Britain’s AI ambitions are realised.
“Digital connectivity must be considered alongside power, planning and other infrastructure priorities,” he said.
Resilience under test
The Budget’s cyber funding comes after the government confirmed on 22 October that 32 services had been taken offline while PHP2Shell patches were applied, though it said it was not aware of any confirmed compromise of central government systems. Michael Vallas, global technical principal at Goldilock Secure, said success should be measured by “how much of the country is resilient”, not only how many attacks are prevented.
Related stories

ITW Asia 2026
ITW Asia brings together the whole connectivity and digital infrastructure industry to get business done. Join 1700+ leaders from carriers, MNOs, cloud solution providers, hyperscalers, content service providers, data centres, satellite operators, investors, regulatory authorities and more, to define the future of connectivity in Asia.