BUZZ’s Tavares: Oakville taxpayers won’t pay grid costs for C$3.5bn, 320MW AI campus

09 October 2026
4 minutes
After Oakville imposed Ontario’s first data centre moratorium, the President and COO of BUZZ HPC sets out who pays for the grid, when water and noise figures will come, and what a Canadian standard should include
Craig Tavares
Craig Tavares

BUZZ High Performance Computing will privately fund the electrical connection, transformer infrastructure, required grid expansions and a new fibre-optic backbone for its proposed AI campus in Oakville, Ontario, according to Craig Tavares, President and COO of BUZZ HPC.

“None of those costs will fall on municipal taxpayers or be recovered through a project-specific increase to residential electricity rates,” he told Capacity.

The commitment comes after Oakville became the first Ontario municipality to impose a one-year moratorium on data centres, three months after BUZZ unveiled the C$3.5bn, 320MW campus. The bylaw runs until August 2027 and can be extended to two years in total, putting pressure on BUZZ’s target of operations in the second half of 2027. No formal application has been submitted.

Figures still to come

Tavares said the campus would connect to the provincial transmission grid rather than Oakville’s local distribution system, with the transformer station on BUZZ’s own property. The formal application will disclose expected electricity demand, connection phasing and grid impacts, he said, though he did not commit to publishing the grid connection agreement itself.

“We want residents to be able to check our commitments for themselves,” he said.

Projected water use and noise levels have not yet been published, with detailed engineering still under way. Tavares said closed-loop liquid cooling means the campus would not need a continuous supply of municipal water for cooling, and that the engineering package will quantify annual top-up water and any discharge. BUZZ will set a noise target below municipal and provincial limits, with independent testing before and after the campus starts running.

BUZZ has also offered Council an independent technical expert, separate from its design team, to review its studies.

A Canadian standard

BUZZ is an original signatory to Canada’s Responsible Data Centre Development Principles, a voluntary framework launched in September. Tavares said BUZZ would welcome clear, enforceable standards and argued Canada could go further than the US Ratepayer Protection Act, which would only have required states to consider large-load standards and was blocked in the Senate last month.

“Where Canada could lead is at the community level,” he said, proposing a standard that includes:

  • independent technical review of key studies before approval
  • measurable conditions on noise, vibration, water, energy, emissions and traffic
  • testing once the facility is running, with corrective action if a target is missed
  • public reporting of verified performance over time.

No waste heat partner yet

Tavares argued AI campuses should sit near the people who use them, pointing to Oakville’s position in the Toronto-Waterloo corridor near universities, hospitals and advanced manufacturers.

“Advanced computing operates optimally when it is located close to the people who rely on it,” he said.

But waste heat reuse, one of the main arguments for building near communities, remains unresolved. “We don’t have a named waste heat partner today,” Tavares said, adding that district energy and waste-heat recovery are among the options BUZZ is exploring.