Data centre developers that treat community engagement as a box-ticking exercise are paying for it, according to EdgeCore Digital Infrastructure. At least 75 US data centre projects worth around $130bn were blocked or delayed by local opposition in the first three months of 2026, according to Data Center Watch, a tracker run by 10a Labs.
Bill Jabjiniak, SVP of National Community & Government Relations at EdgeCore Digital Infrastructure, told Capacity that some developers see community involvement “as just a formality rather than a cornerstone” of their strategy.
EdgeCore, which reports more than 1.8GW of capacity delivered or under development across six North American markets, has never cancelled a project because of community opposition, he said. He credited this to building relationships with local groups before development starts. “It is not about changing a community but about becoming an integral part of it,” he said.
The comments come as opposition hardens into a financing issue. Lenders have started pricing community opposition into data centre deals, and community benefit agreements are replacing tax breaks as the price of site approval.
Community-identified needs
Jabjiniak drew a line between genuine community benefit and PR-led sponsorship. The test, he said, is “whether you’re listening first or leading with a predetermined agenda.”
In Storey County, Nevada, county officials raised public safety as a priority. EdgeCore responded by funding additional radio equipment for first responders, and later a search-and-rescue vehicle for the county sheriff’s office, built for the region’s mountain terrain.
In Arizona, EdgeCore contributed $288,419 to Salt River Project’s Dude Fire Restoration Project, which is clearing hazardous vegetation from a 1990 burn scar north of Payson to protect forest and watershed health. It has committed a further $280,560 to the project’s third phase.
Jobs and the economic case
Permanent headcount remains a weak point in the industry’s pitch to communities. Jabjiniak did not give a figure for long-term roles per campus. He argued instead that the full build cycle should be counted: a gigawatt-scale campus can take ten years or more to complete and employs several thousand construction and engineering specialists over that period.
He also pointed to jobs at tenant companies and local suppliers, and to property and equipment tax revenue that funds schools and infrastructure.
Ratepayer pledge
EdgeCore signed the White House-backed Ratepayer Protection Pledge on 13 August. Signatories commit to bring, build or buy their own power, pay for new delivery infrastructure, and invest in local jobs and workforce development.
Jabjiniak said the pledge required no change to EdgeCore’s processes. The company already requires operators to cover the cost of the power infrastructure that serves them “instead of imposing the cost on local citizens,” he said.
He did not say whether the pledge should become a regulatory requirement. The pledge is voluntary and carries no federal penalty. A proposed Ratepayer Protection Act was introduced in Congress in June.
Skills gap
Jabjiniak named electricians, HVAC specialists and operations technicians as the industry’s biggest shortages. EdgeCore recently joined the US Department of War’s SkillBridge programme, which places service members in civilian training during their final months of service. The company also runs its own Core Operations Apprentice Technician (COAT) programme, which trains people with no prior data centre experience for operations roles, and graduated its first apprentice this year.
“Our goal is simple: to build a local workforce, create long-term career opportunities, and keep those jobs in the communities where we operate,” he said.
Related stories
- What $169m buys you: The new cost of community consent
- Lenders start pricing community opposition into data centre financing as $130bn in projects stall
- What is the Ratepayer Protection Pledge, and why does it matter for data centres?
- Trump blasts communities resisting data centres but the backlash shows no sign of budging
- The data centre dilemma: Fuelling the economy and facing local fury
- EdgeCore’s $17bn+ Louisa County campus
- New York just changed the rules for every data centre on earth

Capacity Europe 2026
The 25th anniversary edition of Capacity Europe 2025 will bring together 3,500+ decision-makers from the global connectivity and digital infrastructure community.