Data Centres

Huang backs neocloud demand as UK grid stalls Nscale’s Essex site

22 October 2026
4 minutes
Nvidia’s chief executive says neocloud funding pressure reflects strong demand rather than structural weakness, days after Microsoft walked away from Nscale’s Essex project amid power delays
Jensen Huang Nvidia
Jensen Huang Nvidia

Nvidia CEO Jensen Huang has said demand for AI compute will see neocloud providers through rising financing pressure, as UK grid constraints leave one of the country’s flagship AI data centre projects facing a wait for power that could run into the next decade.

Speaking to press at GTC Berlin, Huang said Nvidia had “invested enough” in neocloud providers. He described demand for their capacity as “incredible”, with operators “completely sold out”.

“You can’t solve the absence of demand,” he said, arguing that the need for capital and working capital follows from strong demand rather than any structural weakness in the model.

Nvidia’s support has gone beyond equity. The company has begun guaranteeing utilisation floors for neocloud partners such as Sharon AI, agreeing to rent idle capacity if customer demand falls short.

His comments came days after Microsoft withdrew from its agreement to anchor Nscale’s planned data centre in Loughton, Essex, weeks before the neocloud’s planned US listing. The site has been told grid power may not arrive until the early to mid-2030s. Loughton was first announced in January 2025 as a 50MW site scheduled to go live in Q4 2026.

Nscale told Reuters its relationship with Microsoft remained strong and that the grid issue had no impact on its other contracts. Nscale said it remained committed to the Loughton project and was exploring alternative power sources.

Asked whether Nvidia could do more to help Nscale bring its UK sites online, Huang offered encouragement, saying the work was hard and that there was no substitute for it. He described the systems as the largest in the world and difficult to integrate, alongside construction and supply chain pressures. He added that timelines had compressed sharply: three years was once an acceptable build time, while customers now expect sites running within six months.

A standard architecture

Huang said Nvidia’s position as a common platform across cloud providers in every country gave it flexibility when individual projects slip. If one site is delayed, he said, Nvidia can shift compute to another customer so that supply comes online as quickly as possible.

He also pointed to DSX pod, Nvidia’s containerised AI factory unit built within the supply chain, as a way to simplify planning and deployment. The first unit is expected towards the end of the year. However, he acknowledged that faster manufacturing does not remove the need for more energy.

Huang described AI’s demand for power as the best opportunity in a century for market-driven investment in sustainable energy, from nuclear and fusion to grid management technology.

Grid is the variable

The Loughton delay highlights the gap between that demand and the infrastructure needed to serve it. At a Capacity roundtable in London last week, 70% of infrastructure leaders said they expected grid connections to take more than 18 months.

Neoclouds typically carry high capital costs, concentrated customer bases and hardware plans tied to specific sites, which leaves them more exposed when grid connections slip. For Nvidia, a delayed site can mean supply is redirected elsewhere. For a neocloud, or a national AI programme built around domestic capacity, a missed grid date can mean a lost customer.

Loughton follows an earlier setback for Nscale’s UK plans. In April, OpenAI paused its proposed UK Stargate project with Nvidia and Nscale, citing high energy costs.

Nscale has said it is pursuing alternative power for the Essex site. But on-site generation brings its own queue: speakers at Capacity Europe said generator lead times now run to two years. Whether alternatives can close a gap measured in years, rather than months, is likely to shape how much of the UK’s AI infrastructure pipeline is delivered on schedule.

Related stories

mc-usa

Metro Connect USA 2027

08 February 2027

Metro Connect USA is the largest executive-level digital infrastructure event in the U.S. The only one of its kind, this 25-year-strong gathering is where decision makers come together to make deals happen.