It is a sharp step up for a country whose government data sits in a single 6MW facility, but power, financing and connectivity will decide whether the timeline holds.
Kazakhstan plans to commission 186MW of data centre capacity in 2027 and another 109MW in the second quarter of 2028, Deputy Prime Minister and Minister of Artificial Intelligence and Digital Development Zhaslan Madiyev told a government meeting in Astana on 6 October.
The build is centred on Data Center Valley, a campus in Ekibastuz in the Pavlodar region designed to scale to at least 1GW. Madiyev said land has been allocated, an operator selected and engineering infrastructure put in place, including power from the Ekibastuz GRES-1 plant, and that construction of the first facilities has begun.
He also cited the $10bn package of agreements signed with US-based AI cloud company Firebird, and said more than 20 international technology companies and investors have expressed interest in the project.
From 6MW to 1GW
The scale of the jump is the story. Prime Minister Olzhas Bektenov has said all Kazakh government data is currently stored in a single 6MW data centre in Astana.
President Kassym-Jomart Tokayev announced Data Center Valley in January 2026. Its anchor is a 50MW AI-focused facility being built by national operator Kazakhtelecom, due for commissioning by June 2027. In August, the government said excavation for the site’s energy centres and AI factories was 90% complete, with the main buildings and power units due to be finished by the end of 2026.
Madiyev has framed the project in export terms. “Data Center Valley is shaping Kazakhstan’s new export potential,” he said in August.
Kazakhstan is not starting from zero on compute. Two Kazakh systems, Alem.Cloud and AI-Farabium, appeared on the June 2026 TOP500 list of supercomputers at 104th and 122nd respectively, both running on NVIDIA H200 accelerators.
What the $10bn buys
The Firebird agreements, signed in June with NVIDIA’s involvement, are intended to fund a cluster of 100,000 GPUs, including NVIDIA GB300 and Vera Rubin. Madiyev has said the project could generate at least $3bn a year in export revenue.
The package comprises a strategic cooperation agreement between the AI ministry and Firebird, which also creates Firebird Labs Kazakhstan at Alem.ai, and a binding term sheet between Kazakhtelecom and Firebird setting out the technical and organisational terms for Data Center Valley.
Under the model, Kazakh state entities provide power, cooling and connectivity, while Firebird finances the AI infrastructure, including the chips. The first phase is a 125MW facility valued at around $5bn. Firebird co-founder Razmig Hovaghimian has said the 2027 launch would put Kazakhstan “among the world’s top ten countries in AI infrastructure”.
The $10bn headline needs reading with care. Analysis from the Caspian Policy Center, a Washington-based think tank, noted that the Astana agreements did not include binding investment.
Firebird’s record in the region gives the plan some weight. In August the company opened what NVIDIA described as the CIS region’s largest AI factory, in Hrazdan, Armenia, with a target of more than 70,000 NVIDIA Rubin and Blackwell GPUs and 300MW there by the end of 2027. Firebird said NVIDIA intends to invest in the company, which is pursuing a roughly 2GW roadmap across Armenia, Kazakhstan and other markets.
A crowded field
Firebird is not the only foreign player. In May the AI ministry signed with London-based JMOT04 for a Tier IV data centre costing up to $1.5bn. Singapore’s GK Hyperscale is building two data centres in the Akmola and Karaganda regions, and China’s SuperX AI Technology is considering a 1GW AI cluster in the country.
That mix of US, Singaporean and Chinese capital reflects Kazakhstan’s pitch: available land, investment incentives and competitive power, packaged as a neutral hub between East and West.
Neighbours are pursuing the same idea. Uzbekistan is launching a hyperscale data centre zone in Karakalpakstan and Tajikistan has set up an AI special zone, though the Carnegie Endowment has noted that Central Asia’s data centre capacity remains limited overall.
Power is the pressure point
Ekibastuz was chosen because it is one of Kazakhstan’s main energy hubs, built around coal-fired generation. That solves the immediate supply question but raises others.
By the Times of Central Asia’s estimate, a 250MW complex running around the clock would consume about 2.19 billion kWh a year, roughly 1.8% of Kazakhstan’s total electricity use in 2025. Earlier this year Kazakhstan also cancelled contracts with a Russian firm to build and upgrade power plants, re-awarding much of the work to Chinese companies, Eurasianet reported.
The timeline is tight. By mid-2027, Ekibastuz has to turn an excavation site into an operating 125MW facility with power, cooling, fibre and compute in place.
The route west
Compute is only half the equation. Madiyev also said on 6 October that the Trans-Caspian fibre-optic line between Kazakhstan and Azerbaijan is scheduled to launch this month, with 390km of cable already laid between Sumgayit and Aktau.
The system, developed by Kazakhtelecom and AzerTelecom, is designed for around 400Tbps and forms part of the Digital Silk Way corridor running on through Georgia and the Black Sea to Europe.
The two projects are closely linked. Analysis from the Jamestown Foundation argued that without a sovereign east-west fibre route, new Central Asian data centre capacity would still depend on Russian-controlled networks for international transit. On that reading, the cable is what could turn Ekibastuz from a domestic sovereign AI project into capacity that serves customers in Europe and beyond.
What to watch
Three factors will decide whether Kazakhstan hits its numbers: whether Firebird’s framework converts into committed capital, whether Ekibastuz’s power and grid upgrades keep pace with construction, and how much international traffic the Trans-Caspian cable carries once it is live. The first 50MW, due by June 2027, will be the first real test.