Google will invest $15bn in Malaysia across 2027 and 2028, building new data centre campuses as the country tightens the rules on who gets power and water to run them.
The package, announced in Kuala Lumpur on 4 November with prime minister Anwar Ibrahim present, covers data centre campuses, more than 1GW of new clean energy capacity for the national grid, water security projects and training for 800,000 Malaysians by 2031, according to Google. It builds on the $2bn Google committed in 2024 for its first Malaysian data centre and cloud region at Elmina Business Park, Selangor.
Google said construction would add an average of $1.1bn a year to Malaysia’s GDP and support more than 37,000 jobs a year, with the campuses running at a power usage effectiveness of 1.12 to 1.14. Ruth Porat, president and chief investment officer of Alphabet and Google, said the company would be adding “local power and water resources as our operations scale”.
A market that has started saying no
Malaysia’s approvals have been narrowing for some time. Anwar told parliament in February that proposals for data centres unrelated to AI had not been approved for close to two years. On 28 October, deputy prime minister Fadillah Yusof, who is also minister of energy transition and water transformation, said projects in areas with low water reserve margins would not be considered, and that data centres must hold two days of water reserves and source at least 30% of their energy from renewables.
Johor’s state coordination committee reportedly rejected around 30% of data centre applications in 2024 for failing sustainability requirements. BMI, a unit of Fitch Solutions, cites the figure as evidence of a shift from broad investment promotion to a more selective model.
Johor, the country’s main hub, now runs a special technical committee that assesses every proposal on water demand, electricity demand, utility infrastructure and site suitability, The Edge reported.
The pressure shows in the vacancy figures. Johor has the largest incoming data centre pipeline of the Asia-Pacific markets in Knight Frank’s Data Centre Atlas 2026, at 8,542MW, but a colocation vacancy rate of just 0.7%. Singapore’s rate is 4.9%, Jakarta’s 20.5% and Bangkok’s 23.3%. Johor’s live IT capacity stood at 1,110MW at the start of the year, about 13% of what is in the pipeline.
Power and water: the numbers behind the ceiling
Peak electricity demand from data centres in Peninsular Malaysia is projected to reach 8.39GW by 2030, the Ministry of Energy Transition and Water Transformation (Petra) told parliament in October. Johor accounts for 4.42GW of that and Selangor 1.48GW.
Water is the sharper constraint. Petra projects data centre water demand in Johor and Selangor will reach 389.04 million litres a day (MLD) by 2030, against 63.90 MLD consumed today, a six-fold increase.
The deputy prime minister told parliament in July that data centres are forecast to account for a third of Malaysia’s total energy consumption by 2035, AFP reported.
Google’s pledge of 1GW of clean generation is a response to exactly that arithmetic. A hyperscaler bringing its own power and water to the table is becoming the price of entry.
Investment moves beyond Johor
Google’s new campuses are not in Johor. Alongside Elmina in Selangor, the company bought 389 acres in Port Dickson, Negeri Sembilan, in 2025 for a second site.
Others are moving the same way. As land, power and water tighten in Johor and the Klang Valley, investor interest is spreading to other states, Knight Frank said in August. Sarawak’s premier confirmed in October an AI data centre plan as part of a $50bn investment, though the company involved was not named.
Malaysia still accounts for more than half of the data centre capacity under construction across Southeast Asia, according to DC Byte. The question is no longer whether demand exists, but which states can supply the megawatts and the water to meet it.
From Singapore to Johor, and beyond
Singapore’s 2019 moratorium on new data centres pushed demand across the Strait to Johor. Six years on, Johor’s own limits are pushing it further, to Negeri Sembilan, Selangor and Sarawak.
The timing adds another layer. Voters in the US backed 33 data centre curbs in this week’s midterms, and investors are already pricing US political risk into Asia’s AI supply chain. Asia’s markets may be the beneficiaries, but Malaysia shows that even the most welcoming governments are now rationing capacity, through regulators rather than referendums.
That shift, from local planners to energy regulators and central government, is one Capacity has tracked across markets, and it matches the pattern of opposition we found by country: quieter in Asia, but not absent.
The debate heads to Singapore
Power was named the number-one constraint on large-scale builds at ITW Asia 2025, and it runs through this year’s programme at ITW Asia and Datacloud Asia, 1 to 3 December at the Shangri-La Singapore.
- Power: from access to on-site generation (2 December, 14:45, Datacloud Stage): NTT GDC, Oracle, Celera Infrastructure and Iron Mountain on transmission constraints, equipment lead times and new utility partnership models.
- Is the AI race becoming a power race? (3 December, 10:00, Workshop Room 1): AirTrunk, K2 Data Centres, InterContinental Energy and Skeleton Technologies on how energy availability is reshaping site selection.
- Unlocking capital (2 December, 14:00, Datacloud Stage): DigitalBridge, Cushman & Wakefield, OCOLO, Standard Chartered and Aon on financing structures.
- From Brag-a-Watts to Bankable Megawatts (1 December, 09:15, Workshop Room 1): separating headline announcements from capacity that can actually be powered and delivered.
- Streamlining permitting and overcoming community resistance (2 December, 16:10, Datacloud Stage).
See the full rundown in Capacity‘s ITW Asia 2026: 8 sessions to watch in Singapore.
Related stories
- ITW Asia 2026: 8 sessions to watch in Singapore
- The forces shaping Asia’s connectivity market in 2026
- Why power regulators now decide where AI data centres go
- 833 opposition groups, one global pattern: Why data centre resistance looks so different by country
- In data centre development, what are investors prioritising?
- Data centres’ net new power deals with utilities and hyperscalers
- Microsoft and Lightstorm’s I-2SEA cable

ITW Asia 2026
ITW Asia brings together the whole connectivity and digital infrastructure industry to get business done. Join 1700+ leaders from carriers, MNOs, cloud solution providers, hyperscalers, content service providers, data centres, satellite operators, investors, regulatory authorities and more, to define the future of connectivity in Asia.