Microsoft has pulled out of its agreement to anchor Nscale’s planned data centre in Loughton, Essex, where it was due to rent 23,040 Nvidia GB300 GPUs from the first quarter of 2027.
The site has been told grid power may not arrive until the early-to-mid 2030s. The exit lands as Nscale prepares a US listing that could raise up to $3bn, at a reported valuation of up to $35bn.
Nscale has confirmed the withdrawal but given no reason. Microsoft has not commented. An Nscale spokesperson said the relationship remains “strong and long-term” and described the problem as a “London-wide grid issue” with no impact on other contracts.
Power, not demand
Nothing in the reporting suggests Microsoft’s appetite for compute has fallen. Microsoft has signed statements of work with Nscale worth up to $43.8bn through December 2033, and it remains on board for Nscale’s Norway project.
The constraint at Loughton is electricity. A 23,000-GPU deployment due in early 2027 cannot wait for a grid connection pencilled in for the next decade. For a hyperscaler with sites across the world, the rational move is to place that capacity where power already exists.
Loughton is not an isolated case. Ofgem has said the UK grid connection queue grew 460% in the first half of 2025, with data centres accounting for at least 73GW of the pipeline. At a recent Capacity roundtable in London, 70% of infrastructure leaders said they expect grid connections to take more than 18 months.
The same pattern surfaced on the other side of the world on the same day. Australian operator NextDC halted its shares on 19 October while it assesses a power supply delay at its M3 Melbourne data centre, including the impact on FY27 guidance.
Two markets, two operators, one bottleneck. The AI build-out is increasingly limited by when and where power can be connected, not by how many chips customers want.
Concentration risk
Microsoft and Anthropic account for about 85% of Nscale’s contracts, according to its IPO filing. That leaves the company exposed to the decisions of two customers.
The Telegraph reported that Microsoft alone accounts for more than 40% of Nscale’s $103bn in contracted revenue, though the Loughton deal is believed to be a small part of that. The filing does not show how much of Microsoft’s commitment, if any, was tied to the Essex site.
The direct financial hit may therefore be modest. The signalling effect is harder to contain. Loughton was Nscale’s only publicly announced customer for the site, and its first owned UK data centre. Investors weighing a $3bn raise will ask how firm the rest of a two-customer backlog really is.
Contract concentration among a handful of hyperscale customers has been emerging as the sector’s central vulnerability, as Capacity has previously reported. It also sits alongside the circular financing ties between Nvidia and the neoclouds it backs, Nscale included.
Delivery record
Loughton is not Nscale’s only timing problem. Its flagship site in Norway is six months behind schedule, with 6.4MW of a planned 30MW running, Bloomberg reported.
Loughton itself has slipped more than once. When Nscale unveiled the site in January 2025, it was a 50MW facility, scalable to 90MW, due to go live in the fourth quarter of 2026. That date later moved into 2027, and by the summer the site faced further power delays.
For a company asking public markets to value it at up to $35bn, more than double its $14.6bn valuation at its $2bn Series C in March, execution matters as much as contracted revenue. A backlog is only worth what can be powered and delivered.
Market mood
The timing compounds the problem. Neocloud sentiment has soured in recent weeks: CoreWeave shares fell 25% last week, and Australia’s Nvidia-backed Firmus scrapped its planned IPO after failing to attract enough demand at its proposed valuation.
Neoclouds have pitched themselves as the fastest route to GPU capacity for hyperscalers and AI labs. That pitch depends on delivering powered capacity on time. When sites slip and anchor tenants walk, investors start pricing in delivery risk alongside demand risk.
Financing pressure adds to the strain. CoreWeave, the largest listed neocloud, reported total debt of $35bn at the end of June, much of it maturing between 2026 and 2028.
The UK policy question
Loughton carried political weight beyond Nscale. It formed part of Microsoft’s £22bn UK infrastructure pledge announced during President Trump’s state visit. The government had billed it as the “largest UK sovereign AI datacentre”.
If the UK’s most prominent sovereign AI project cannot secure a grid connection before the 2030s, the gap between national AI ambitions and grid delivery is no longer theoretical. Nscale says it is exploring alternative power sources for the site. Capacity reported this summer that it was in talks with Bloom Energy over on-site fuel cells. That route adds cost and planning complexity.
Policy is starting to respond. Ofgem has proposed a Data Centre Commitment Fee to clear speculative projects from the queue, and the government has unveiled GB Grid, a state-owned transmission challenger that could let developers build their own connections. Neither will help Loughton in time for 2027.
What to watch
- The IPO filing. Whether Nscale updates its risk factors or customer disclosures before pricing, and whether the listing timetable holds.
- Loughton’s power plan. Whether Nscale names an alternative power source, a new tenant, or a revised delivery date.
- Microsoft’s next move. Whether the 23,000 GPUs land at another Nscale site or with another provider.
- NextDC’s update. Due by Wednesday 21 October, when its trading halt ends, and a second read on how far power delays are reaching into guidance.
- GTC Berlin. Nvidia’s European conference runs 20 to 22 October. Expect questions on how Nvidia-backed neoclouds secure power, and on sovereign AI in Europe.
Related stories
- UK’s ‘largest AI supercomputer’ by Nscale could be delayed… again
- UK government reportedly urged Nscale AI data centre approval
- Nscale’s $900m credit facility promises to scale AI data centres
- Nscale bags $2bn in funding as ex-deputy PM Nick Clegg joins board
- What is a neocloud, and why does it matter for digital infrastructure?
- What is circular financing in AI infrastructure?

Capacity Europe 2026
The 25th anniversary edition of Capacity Europe 2025 will bring together 3,500+ decision-makers from the global connectivity and digital infrastructure community.