Shares closed down 41.7% at A$5.35, their lowest level since 2018, after NextDC told the ASX that electricity distributor Jemena had suspended parts of the 66kV network works needed to increase grid supply to its M3 data centre in West Footscray. Jemena does not expect to restart before February 2027, pushing the next increase in supply into FY28.
Chief executive Craig Scroggie said Jemena had “suspended parts of the network works” required for the next step up in supply to M3.
As a result, NextDC removed the affected M3 customer contracts, worth about A$140m in both net revenue and underlying EBITDA, from its FY27 guidance. Underlying EBITDA guidance fell to A$245m to A$265m, from A$385m to A$410m, a cut of around 36%. Net revenue guidance fell to A$475m to A$500m, from A$615m to A$640m.
The company also trimmed capex guidance to A$4.5bn to A$5bn, from A$5.25bn to A$5.75bn, and put all new development projects and land acquisitions on hold. The revised capex range includes around A$230m of capitalised interest that the previous guidance did not.
A power problem, not a demand problem
The downgrade has nothing to do with customer appetite. M3 has a total planned capacity of 225MW, and construction of its data halls is continuing. The issue is getting power to it.
According to NextDC, Jemena attributed the suspension to safety concerns, a lack of access to work sites caused by community and stakeholder opposition, and the local council, as road authority, withholding consent while further consultation takes place.
The works involved replacing power poles in Yarraville and West Footscray with much larger poles able to carry 66kV lines. In September, residents blocked Jemena crews by leaving their cars and bins in the way.
M3 has operated since 2022 and sits about 15 metres from homes. It has long faced local opposition over diesel and noise pollution, and campaign group Citizens of Tottenham has welcomed NextDC’s setback. A Victorian government decision on a permit for the site’s next stages, lodged in February, is now not expected until 2027, after the state election on 28 November.
From planning risk to balance-sheet risk
What sets the NextDC case apart is where the risk landed. Community opposition to data centres is usually discussed as a planning or permitting issue. Here, it reached revenue already under contract.
NextDC said the affected contracts provide for service-level credits where capacity is delivered late or not fully powered and, in some circumstances, give the customer the right to terminate. It is considering whether force majeure or other provisions offer relief. Its revised guidance even excludes capacity that is already billing, because existing grid supply cannot be relied on to support the full contracted power ramp.
The company also warned that a material change to expected customer billing, such as the M3 delay, could affect its ability to draw down its A$6.7bn of undrawn senior debt while staying within covenants. It reported liquidity of A$8.68bn at 30 September and says it complies with its financial covenants.
Reuters Breakingviews pointed to delay clauses in data centre contracts that can let a customer cancel entirely if completion runs more than 12 months late. For operators building against hyperscaler deadlines, that turns a local dispute over poles into a question of contract enforceability.
NextDC is not the first operator to reach for force majeure. Oracle has already issued a force majeure notice over power delays at its Project Jupiter campus in New Mexico, preserving the right to defer rent if the site misses its 2028 start.
A market divided
Analysts are split on whether the sell-off went too far. RBC Capital Markets analyst Tom Beadle said the delays were outside NextDC’s control, but showed that community concerns are a real risk to the timing of contracted capacity for data centre owners.
According to market commentary site The Bull, Macquarie retained its Outperform rating but cut its price target by 35% to A$12.90, and lowered its EBITDA forecasts by 35% for FY27 and 23% for FY28. It argues NextDC does not need to raise equity, with interest cover of 1.67 times in its bear case, above the 1.5 times covenant threshold.
Shares recovered 7.5% to A$5.75 on 22 October, but remain well below their level before the announcement.
Not just a US story
Community opposition to data centres has largely been framed as a US phenomenon. NextDC suggests it is spreading to markets once seen as lower-risk, and that the flashpoint is increasingly the grid connection rather than the building itself.
Europe is not immune. Finland has ordered Google to halt construction at two data centres after more than 300 hectares of forest were cleared. At a Capacity Europe roundtable this month, 70% of infrastructure leaders said they expect grid connections to take more than 18 months.
Canada offers another test. EverWind is proposing a data centre at Point Tupper, Nova Scotia, to be leased for 20 years to Anthropic, with a 95MW first phase and plans for a 325MW expansion by mid-2028. EverWind calls it the largest private investment in the province’s history, but a petition against it gathered more than 18,000 signatures within a week.
Tech critic Paris Marx has argued that opposition is forming quickly in Canada because communities have already watched how projects played out in the US. In Ontario, Oakville has already imposed the province’s first data centre moratorium, putting the question of who pays for grid upgrades at the centre of the debate.
For developers, the NextDC episode raises a practical question: whether social licence for grid works now needs to be secured as early, and as carefully, as power capacity itself. EdgeCore’s Bill Jabjiniak has argued that the scale of stalled projects shows developers treat communities as a formality.
Related stories
- $165bn Project Jupiter: What Oracle’s force majeure notice means for AI data centre risk
- EdgeCore: ‘$130bn of stalled projects shows developers treat communities as a formality’
- When does a license to operate go beyond official sign-off?
- 70% of infrastructure leaders at London roundtable expect grid connections to take more than 18 months
- BUZZ’s Tavares: Oakville taxpayers won’t pay grid costs for C$3.5bn, 320MW AI campus
- Finland stops construction on two Google data centres
- Large-scale data centre planned for former Scottish nuclear site
Nvidia CEO Jensen Huang has said demand for AI compute will see neocloud providers through rising financing pressure, as UK grid constraints leave one of the country’s flagship AI data centre projects facing a wait for power that could run into the next decade.
Speaking to press at GTC Berlin, Huang said Nvidia had “invested enough” in neocloud providers. He described demand for their capacity as “incredible”, with operators “completely sold out”.
“You can’t solve the absence of demand,” he said, arguing that the need for capital and working capital follows from strong demand rather than any structural weakness in the model.
Nvidia’s support has gone beyond equity. The company has begun guaranteeing utilisation floors for neocloud partners such as Sharon AI, agreeing to rent idle capacity if customer demand falls short.
His comments came days after Microsoft withdrew from its agreement to anchor Nscale’s planned data centre in Loughton, Essex, weeks before the neocloud’s planned US listing. The site has been told grid power may not arrive until the early to mid-2030s. Loughton was first announced in January 2025 as a 50MW site scheduled to go live in Q4 2026.
Nscale told Reuters its relationship with Microsoft remained strong and that the grid issue had no impact on its other contracts. Nscale said it remained committed to the Loughton project and was exploring alternative power sources.
Asked whether Nvidia could do more to help Nscale bring its UK sites online, Huang offered encouragement, saying the work was hard and that there was no substitute for it. He described the systems as the largest in the world and difficult to integrate, alongside construction and supply chain pressures. He added that timelines had compressed sharply: three years was once an acceptable build time, while customers now expect sites running within six months.
A standard architecture
Huang said Nvidia’s position as a common platform across cloud providers in every country gave it flexibility when individual projects slip. If one site is delayed, he said, Nvidia can shift compute to another customer so that supply comes online as quickly as possible.
He also pointed to DSX pod, Nvidia’s containerised AI factory unit built within the supply chain, as a way to simplify planning and deployment. The first unit is expected towards the end of the year. However, he acknowledged that faster manufacturing does not remove the need for more energy.
Huang described AI’s demand for power as the best opportunity in a century for market-driven investment in sustainable energy, from nuclear and fusion to grid management technology.
Grid is the variable
The Loughton delay highlights the gap between that demand and the infrastructure needed to serve it. At a Capacity roundtable in London last week, 70% of infrastructure leaders said they expected grid connections to take more than 18 months.
Neoclouds typically carry high capital costs, concentrated customer bases and hardware plans tied to specific sites, which leaves them more exposed when grid connections slip. For Nvidia, a delayed site can mean supply is redirected elsewhere. For a neocloud, or a national AI programme built around domestic capacity, a missed grid date can mean a lost customer.
Loughton follows an earlier setback for Nscale’s UK plans. In April, OpenAI paused its proposed UK Stargate project with Nvidia and Nscale, citing high energy costs.
Nscale has said it is pursuing alternative power for the Essex site. But on-site generation brings its own queue: speakers at Capacity Europe said generator lead times now run to two years. Whether alternatives can close a gap measured in years, rather than months, is likely to shape how much of the UK’s AI infrastructure pipeline is delivered on schedule.
Related stories
- Microsoft’s Nscale exit: A $3bn IPO meets a UK grid problem
- Nvidia now agrees to rent back unused GPU capacity from neocloud operators if customer demand falls short
- 70% of infrastructure leaders at London roundtable expect grid connections to take more than 18 months
- Two-year generator waits push data centre builders to procure before they design
- 10 things we learned at Capacity Europe 2026
- What is a neocloud, and why does it matter for digital infrastructure?

ITW Asia 2026
ITW Asia brings together the whole connectivity and digital infrastructure industry to get business done. Join 1700+ leaders from carriers, MNOs, cloud solution providers, hyperscalers, content service providers, data centres, satellite operators, investors, regulatory authorities and more, to define the future of connectivity in Asia.