Both sessions ran under the Chatham House Rule, so nothing below is attributed to an individual, company or organisation. As a result, this piece runs without direct quotes, in keeping with that condition.
$10-12 a foot: The benchmark for underground fibre builds
Attendees at the Fiber Leaders lunch converged on $10-12 a foot, all-in, as the going rate for underground fibre construction, with one operator citing roughly $700 a home passed as still broadly cost-effective given today’s permitting and labour environment. Micro-trenching came up repeatedly as a way to bring costs down, though the room agreed it works best in warmer, drier markets such as Nevada, Arizona, New Mexico and California, and is harder to justify across the south-central states and the Pacific Northwest.
Builders standardise on 1.5in conduit to future-proof routes
Several operators said they now default to a 1.5in conduit, wide enough to carry 864, 1728 or 3456-count cable, to avoid reopening the same trench for a future upgrade. The trade-off is a familiar one: how much extra capacity to build ahead of confirmed demand, weighed against the capital cost of over-engineering a route on day one.
Lead times and a tightening labour market push builders toward outsourced construction
Cable lead times remain a live pain point, with several attendees saying the only reliable fix is ordering early and warehousing stock, a burden some are now pushing onto construction partners in exchange for a markup on materials. Views were split on in-house versus outsourced construction crews: in-house teams were credited with efficiency and cost control on smaller, high-density builds, while outsourcing was favoured by operators managing volume swings across a wider programme.
A recurring theme was that permitting speed, not materials, is now the primary constraint on build velocity, prompting several operators to invest in software to manage multi-permit applications with municipalities. Capacity’s coverage of Metro Connect Fall, held in Austin the same week, found labour shortages among electricians and fibre construction crews cited as an industry-wide constraint, worsened by Buy America rules and shifting tariffs.
Fibre operators’ eye wholesale deals with hyperscale and AI data centre builders
A significant part of the session focused on the commercial opportunity in serving data centre and hyperscale builds directly, with attendees urged not to overlook operators already constructing nearby, since a wholesale or capacity-sharing arrangement can offset the cost of an otherwise stranded route. Speakers pointed to strong return profiles among data centre operators, particularly on terminal value, as a reason fibre builders may find more room to negotiate funding for non-recurring construction costs than they assume.
A fragmenting pipeline: US data centre capacity splits between hyperscale campuses and smaller regional sites
The Digital Infrastructure Leaders’ Summit opened with data showing planned US data centre capacity fragmenting by geography, from large hyperscale campuses in major metros to smaller, more distributed sites in regional and rural markets. Attendees debated whether AI-driven demand keeps concentrating in gigawatt-scale training campuses, or increasingly shifts toward smaller inference-focused facilities closer to users, with most in the room leaning toward continued growth in both training and inference workloads rather than a slowdown.
M&A cools as roughly half of mid-market data centre providers have already changed hands
Panellists said the wave of M&A that consolidated mid-sized data centre providers over the past five to seven years, with roughly half of the operators serving 250kW-2MW leases in the top 25-50 US markets acquired by larger players, is likely to slow this year as valuations and financing conditions tighten. Even so, competition for the remaining independent assets was described as intense, with buyers said to be scrutinising acquisition targets more carefully than in the recent past.
Behind-the-meter economics: In Texas, gas supply is the binding constraint, not power
A detailed session on behind-the-meter power in Texas highlighted natural gas supply, not electricity capacity, as the real bottleneck: pipeline capacity is typically already committed years ahead to liquefaction terminals or power plants, meaning a data centre sited next to a pipeline cannot assume gas will actually be available.
One operator described taking a large Texas project fully off-grid, building its own turbine generation and even its own sewage treatment, using multiple smaller turbines rather than large combined-cycle units to avoid grid-stability and harmonics issues; the cost figure given for the power build-out was inconsistent in the recording, so it isn’t repeated here. The wider point stood regardless: firm, resilient gas contracts, not just proximity to a pipeline, now determine site viability.
Texas regulators weigh a rule that could bind large loads to transmission costs for up to 20 years
A regulatory update flagged the Public Utility Commission of Texas’s Project 58000, which would replace the current four-coincident-peak transmission charge with a 12-coincident-peak model and introduce a minimum billing demand for large loads, requiring roughly 20 years of payments (240 consecutive monthly instalments) regardless of whether a facility is fully operational.
This is a live, verifiable proceeding: the PUCT published its proposed rule in July 2026, and Senate Bill 6 requires a final rule by 31 December 2026, so the room’s sense that a decision was close tracks with the public timeline. Panellists were split on the fairness of shifting more transmission cost onto data centres, with some arguing new load ultimately lowers system-wide costs by underwriting grid investment, and others noting the change reflects growing pressure from residential and commercial customers to avoid subsidising large loads.
It’s a separate track to Governor Abbott’s ERCOT interconnection audit, which Capacity has covered in detail, but both point the same way: Texas regulators are tightening scrutiny of data centre load on the grid.
$110 million and counting: community benefit agreements become a standard cost of entry
One operator detailed a community benefits package attached to a roughly 2.6-gigawatt project, running to more than $110 million and covering school renovations, a community centre, workforce training, agricultural land preservation and a new fire engine, after what was described as several years of community and legal negotiation. Speakers broadly agreed such packages are becoming a standard, if unevenly applied, cost of large-scale development, and several argued the industry needs more consistent, accountable frameworks for negotiating them rather than ad hoc deals.
25,000 jurisdictions, one framework: A new tool aims to standardise data centre permitting
A new not-for-profit initiative was previewed that packages data centre-specific planning guidance, land use questions and community engagement standards into a single reference document, running to more than 550 pages, alongside an AI-assisted tool that lets both municipalities and developers query it directly.
Organisers said the goal is to move permitting from a reactive, project-by-project process to one where communities set expectations upfront, and said the tool has drawn interest from opposition groups as well as developers, with a public launch planned within the next few months.
Industry associations push for a “single voice” on community and policy engagement
Multiple speakers called for the data centre and digital infrastructure sector to consolidate its advocacy the way the wireless tower industry did in the late 1990s and 2000s, warning that fragmented, company-by-company engagement with communities and legislators is fuelling distrust. Industry bodies represented in the room, several marking a decade of operation this year, pointed to expanding local-chapter networks and new policy and community-facing initiatives as early steps toward a more coordinated approach.
RELATED STORIES
Texas hits pause on its own AI boom: Inside the 300-project grid audit
Why speed to power will define data centres
Trump blasts communities resisting data centres, but the backlash shows no sign of budging
Lenders start pricing community opposition into data centre financing as $130bn in projects stall

Metro Connect USA 2027
Metro Connect USA is the largest executive-level digital infrastructure event in the U.S. The only one of its kind, this 25-year-strong gathering is where decision makers come together to make deals happen.





