Schneider Electric intends to commercialise its Immersive Twin next year, after a pilot that connected real-time power and cooling simulation to a live AI factory in Portugal.
The pilot, announced at NVIDIA GTC Berlin on 21 October, is built on the NVIDIA Omniverse DSX Blueprint. It models Nscale’s operations at SIN01, the 26MW first building on Start Campus’s 1.2GW SINES Data Campus. Nscale plans to deploy more than 66,000 NVIDIA Rubin GPUs on the campus for Microsoft from late 2027, in SIN02, a second building of up to 200MW.
“This is not a one-and-done pilot,” Steve Brown, vice president, EcoStruxure IT Line of Business at Schneider Electric, told Capacity at the event. “We intend to commercialise this through next year.”
The twin is not yet generally available. Brown said commercial discussions are ongoing and Schneider is still working on the exact steps to market.
From reference design to live site
At NVIDIA GTC in San Jose in March, Schneider unveiled a Vera Rubin reference design and a lifecycle digital twin architecture within the DSX Blueprint. That built on the power-focused AI factory twin Schneider launched with ETAP on NVIDIA Omniverse in 2025. Sines is the first time the technology has been applied end to end on a live site, with a developer and its tenant.
Brown said compressed AI factory timelines are driving the shift. Power, cooling and IT are now so closely coupled that “the margin for error is very, very limited”, he said.
Data centre delivery cycles have also fallen out of step with GPU cycles, which are moving far faster. That leaves operators needing to validate decisions before hardware arrives.
Real-time solvers
The twin pairs visualisation in NVIDIA Omniverse with Schneider’s own simulation engines: ETAP for power and EcoStruxure IT for cooling, with AVEVA software linking them. Brown said the real-time connection to those solvers is what separates it from static, CAD-style twins.
He gave a simple example. An operator can drop a Vera Rubin rack into the model in place of a planned Blackwell rack. The twin then runs the change through the power and cooling solvers and returns recommendations or deviations in the same view. The example mirrors Nscale’s own path at Sines, from more than 12,600 Blackwell Ultra GPUs in SIN01 to Rubin from late 2027.
Brown outlined two use cases. During build or refactoring, the focus is “time to token”: testing whether CDUs, piping and upstream electrical infrastructure are sized correctly for new compute. Once a site is operating, the focus moves to token efficiency.
Mapping hidden relationships
Brown said the first challenge was the fidelity of sim-ready assets, the 3D models carrying the properties needed for simulation. Schneider’s experience as a manufacturer helped ensure both its own and third-party assets were accurate enough to simulate against.
The second, which he framed as an opportunity, is that most operators know their data centre at asset level but have not mapped how assets connect. Which switchgear feeds which UPS, busway and rack is often undocumented.
Schneider’s energy intelligence orchestration layer maps those links. That lets operators ask how a CDU set point affects an upstream chiller, for example, and whether power is being stranded as a result.
Three partners, one model
Start Campus supplied the facility, engineering and operational data, Nscale its workload and IT requirements, and Schneider the twin technology. Brown described the result as “one plus one plus one equals more than three”.
Nscale CTO David Power said in the announcement that the twin gives “a clearer view” of where full-stack optimisation can happen before changes are made on the ground.
For Start Campus, the twin is also a sales tool. Asked whether it now forms part of the pitch for Sines against other European sites, Omer Wilson, chief marketing officer at Start Campus, told Capacity: “Absolutely.”
Wilson said the site’s competitive proposition rests on scale, sustainability, connectivity and flexibility. Testing infrastructure in a live AI factory environment adds to that, he said.
Brown said the campus’s long runway was a key reason for choosing it. Start Campus plans to keep building beyond SIN01 towards more than 1GW, so the twin can be reused across successive builds.
Bespoke for now
Each twin remains customised to its site, and the building models ingested will differ for every data centre. Brown said Schneider’s goal is to standardise as much of the core technology as possible, using the Sines pilot as the template.
He added that the platform will stay open and interoperable, and extensible to third-party simulation engines.
“This is a pretty major milestone,” Brown said of getting the twin running on a real data centre.
Related stories
- Data centre of the month: Start Campus SINES development in Portugal
- Schneider Electric, Start Campus debut new AI-ready data centre at Sines, Portugal
- Schneider Electric, ETAP launch digital twin tool for AI data centres
- Microsoft powers into Portugal with €8.6bn AI data-centre hub
- Nscale & Microsoft partner with Nvidia & Caterpillar to scale new AI data centre

ITW Asia 2026
ITW Asia brings together the whole connectivity and digital infrastructure industry to get business done. Join 1700+ leaders from carriers, MNOs, cloud solution providers, hyperscalers, content service providers, data centres, satellite operators, investors, regulatory authorities and more, to define the future of connectivity in Asia.