Two-year generator waits push data centre builders to procure before they design

15 October 2026
6 minutes
Capacity Europe 2026: Speakers on the Scaling Under Scarcity panel said manufacturing capacity, not price, now decides whether AI-era projects are delivered on time
data centre
data centre

Data centre builders are ordering generators two years ahead and committing to suppliers before designs are final, as shortages of power equipment and skilled labour push speed of delivery above cost, according to speakers at Capacity Europe 2026.

On the “Scaling Under Scarcity: Delivering Projects Amid Shortages” panel on the AI Build Stage in London on 14 October, procurement and engineering leaders from Greenscale, Start Campus, Telehouse and Kentik said the industry’s long focus on negotiating the lowest price has given way to securing manufacturing slots.

“We’re worried about cost and lead times, where I believe we should be worried about capacity,” said Miriam van Kooperen, senior director, supply chain at Greenscale.

Power equipment remains the most visible bottleneck, as grid operators and hyperscalers have been discussing all year. Van Kooperen named high-voltage transformers, gas-insulated switchgear and generator engines as today’s shortages, but warned that the gap between fast-moving AI development and available manufacturing capacity is widening, with some suppliers already warning that their capacity is running full.

Ozgur Duzgunoglu, head of engineering and design at Telehouse, said generators can take two years to arrive and high-voltage transformers 12 to 18 months, depending on capacity. In one recent case, his team faced a deadline of the following Friday to order generators that would arrive two years later. Procurement teams must keep chasing manufacturers to protect their production slots, he added, because a hyperscaler can step in and order hundreds more units.

Equipment is only half the problem

Nelson Pinto de Magalhaes, director, PMO and procurement at Start Campus, which is developing a hyperscale campus in Portugal, said long-lead equipment can largely be managed through early commitments. The harder task is making sure equipment, installers and commissioning teams all land in the same window.

He noted that the way AI is deployed changes roughly every six months, while even a fast-tracked data centre takes around 18 months to build. Duzgunoglu agreed that designers and contractors are in short supply, alongside the challenge of bringing grid power to site in time for day one.

Procure first, design around it

Panellists described a fundamental change in how operators contract with suppliers. Van Kooperen said operators now have to secure capacity “without knowing exactly what it is we will be buying”, agreeing a preferred list of vendors and a cut-off date by which designs must be broadly frozen so production can begin. Procurement, she said, is now more about being able to deliver than winning the best commercial deal in the market.

Start Campus has gone further, integrating procurement and design teams so that procurement can lead. “Procure first, design around it” is now one of the company’s mantras, Pinto de Magalhaes said. “You can’t really compress a factory to produce more.”

He said customers judge operators on whether the ready-for-service (RFS) date is met, not on which component arrived late, and that phased RFS allows service to go live while construction continues. He has reframed procurement around time rather than money: “What if everything that we called savings now is days?”

Duzgunoglu said each day saved brings revenue forward and improves returns on borrowed capital, and that cost sometimes becomes secondary to hitting the date. Justin Ryburn, field CTO and VP of global solutions engineering at Kentik, said paying marginally more to bring infrastructure online faster can deliver real value to the business.

When moderator Simon Allen, global ambassador at Nomad Futurist, suggested companies might need a chief time officer, Van Kooperen said procurement leads were already playing that role.

Standardise performance, not products

On design, Duzgunoglu said Telehouse works from a standard design with flexible sub-packages that can be deployed anywhere from Frankfurt or Paris to Thailand, and names four or five suppliers for main packages rather than relying on one. Local supply chains matter: a UPS manufacturer used in Europe would not necessarily be used in Tokyo or Osaka.

Van Kooperen, who said she once urged design teams to standardise, now argues for performance-based rather than product-based specifications, so operators can switch supplier when a preferred vendor cannot deliver.

Pinto de Magalhaes said performance specifications widen the supplier pool but can push risk down to interfaces and commissioning. His approach is to standardise the building blocks so that several suppliers can provide them.

Building differently

Prefabrication is now widely deployed. Duzgunoglu described coolant distribution units for liquid cooling being manufactured off-site and delivered for plug-and-play installation, a change he said saves time rather than cost. Factory testing helps, but some problems only surface on site, and compressed programmes can leave only weeks for commissioning.

For smaller players the squeeze looks different. Ryburn said Kentik, which runs its own bare-metal infrastructure in leased cages, has been told by its data centre provider that space is now sold a floor at a time. The company is now weighing re-engineering its software to run on a hyperscaler that already has capacity.

Ryburn also cited a US data centre customer that runs its generators continuously to bring capacity online before the grid connection is ready, then switches them to backup once grid power arrives. Late power is becoming a contractual risk too: Oracle has issued a force majeure notice over Project Jupiter, its Stargate campus in New Mexico, in case the site’s power supply is not ready for its 2028 start.

Location is becoming a lever of its own. Pinto de Magalhaes said moving to areas with grid availability removes the grid as the main bottleneck. Duzgunoglu said securing power in Frankfurt can take five to seven years, though many customers still want to be in central London, where connectivity and cross-connects are concentrated.

2029: power and people

Asked to look three years ahead, the panel pointed to power and skills. Ryburn expects power to remain the bottleneck for the foreseeable future. Duzgunoglu highlighted green power and a skills shortage in which clients, contractors, designers and suppliers are all competing for the same pool of people.

Van Kooperen said new locations with available power often lack data centre construction experience, and that mechanical, electrical and plumbing (MEP) trades would see the greatest shortages. It is a concern shared across the supply chain: 3C Datalec CEO Steve Walton told Capacity this week that the shortfall of engineers and tradespeople is as significant a constraint as power and equipment.