Data Centres

Why power regulators now decide where AI data centres go

02 November 2026
6 minutes
A paused 1GW campus in Australia, a split approval in Alberta and the UK's new grid covenant point to the same shift: the deciding say over AI data centres is moving from local planners to energy regulators and central government.
data centre countries (1)
data centre countries (1)

A 1GW AI data centre planned for Australia’s Northern Territory has lost its start date, the latest sign that approvals, rather than capital or demand, are setting the pace of the AI infrastructure build.

Energy North told Reuters it is no longer working to the June 2028 first-power date for Project Ares, a solar and gas-powered campus planned for a cattle station almost 700km from the nearest city. The company called the date “indicative” and said it would confirm timing once the Northern Territory Environment Protection Authority (NT EPA) sets terms for an environmental impact statement.

The pattern is not confined to Australia. In Canada and the UK, the decisions that matter most for large AI campuses are increasingly being made by power regulators and central government rather than local planning authorities.

Australia: A regulator waiting on Canberra

In a 7 October ruling, the NT EPA suspended its seven-week deadline for setting assessment terms so it could seek advice from the federal government, which is still developing its policy expectations for data centres, Reuters reported. The regulator identified 10 potential impacts from the roughly 190 sq km campus, from strain on water systems to disruption of Aboriginal sacred sites, and said it had low confidence the proposed measures would manage significant impacts.

Energy North says Project Ares is designed as an off-grid campus with 1GW of IT load, 3,000MWp of solar and 16GWh of battery storage, backed by up to 1,038MW of gas generation for firming. The company declined to identify its financiers to Reuters.

Reuters described the delay as the largest timing setback yet for an Australian data centre. It comes less than two weeks after NextDC lost almost 42% of its market value in a day when community opposition halted grid works at its M3 Melbourne campus. The territory government is reportedly in talks with 12 data centre-related projects.

Alberta: The power plant is approved, the data centre is not

In Alberta, the decisive approval has come from the power regulator. On 23 October, the Alberta Utilities Commission (AUC) approved, with conditions, a 920MW gas plant to supply Beacon Data Centers’ Heartland hub in Sturgeon County, northeast of Edmonton. The decision covers the plant only, not the associated 800MW data centre, although the county has issued a master development permit for the wider project.

Anthropic is in talks to lease the campus, The Globe and Mail reported on 30 October, citing two sources. Both companies declined to comment, and no capacity, term or price has been disclosed. A deal would follow Anthropic’s lease at EverWind’s Point Tupper campus in Nova Scotia, its first in Canada, and its first Australian lease in Queensland.

Sturgeon County already hosts Meta’s 1GW, CAD13bn campus, announced in July. Opposition is building: landowners near Beacon’s planned Indus site, east of Calgary, have contested its gas plant plans there, and Samson Cree Nation, the lone intervenor in the Sturgeon County proceeding, has yet to decide its next step, according to The Globe and Mail. In Ontario, Oakville has imposed the province’s first data centre moratorium.

UK: Grid access becomes the bargaining chip

The UK has gone furthest in turning power into a policy lever. The Data Centre Covenant, published alongside chancellor John Healey’s 28 October Budget, sets five tests covering energy costs, community investment, environmental standards, jobs and security.

Strategic data centres that pass can have grid capacity reserved or reallocated for them, and the most exceptional may get temporary on-site generation until a connection arrives. A Ministerial Control Centre chaired by the minister for AI will decide which sites qualify, but the government has yet to define a strategic data centre.

The cost of waiting is already visible. Microsoft walked away from Nscale’s planned Loughton site after it was told grid power may not arrive until the early-to-mid 2030s. Critics question the trade. Foxglove, a legal firm that challenges data centre plans in court, told The Observer that strategic sites would be “handed a golden ticket to skip the grid connection queue”, with nothing binding them to deliver the promised community benefits.

The risk is starting to be priced

As timelines stretch, the financial sector is adapting. In Singapore, insurers, brokers and industry bodies are developing a regional data centre insurance facility with US$200m of initial capacity, national development minister Chee Hong Tat said on 2 November. Backers include MSIG, Gallagher Re, Scor, Samsung Re and the Cybersecurity Association Singapore, with an MOU due to be signed this week.

The facility will cover construction, operations, supply chain, design and cyber risks. Chee said cover for the sector remains fragmented, and put Asia-Pacific data centre capacity at about 32GW, rising to 57GW by 2030. It follows US lenders pricing community opposition into financing terms.

What to watch

  • Australia: when the NT EPA sets terms for Project Ares’ environmental impact statement, and whether Canberra’s data centre policy lands first
  • UK: the final definition of a strategic data centre, which decides who can use the covenant
  • Alberta: whether Anthropic’s talks with Beacon become a signed lease, and Samson Cree Nation’s next step
  • US: the 3 November midterms, and what the results mean for power costs and project approvals

RELATED STORIES

itw-asia-new-logo

ITW Asia 2026

01 December 2026

ITW Asia brings together the whole connectivity and digital infrastructure industry to get business done. Join 1700+ leaders from carriers, MNOs, cloud solution providers, hyperscalers, content service providers, data centres, satellite operators, investors, regulatory authorities and more, to define the future of connectivity in Asia.